Will my lot be ready to build on after clearing?
No — and this is the most important thing to be clear about. Clearing gets the vegetation off. A buildable pad requires stump removal, grading, and compaction to a spec, and that is grading-contractor work that comes after us.
What clearing does give you is decision-making ability. Most people choose a house site far better after the brush is off than they did from a satellite image, because they can finally see the slope, the drainage, the rock, and the trees worth keeping.
If someone tells you a mulching pass produces a building pad, get that in writing, then get a second opinion.
What order should site prep happen in?
In most cases: survey and boundaries, then clear enough to see and access the site, then site evaluation (septic, soils, drainage), then final tree decisions, then stump removal and grading.
Clearing early in that sequence is what makes the later steps accurate. Evaluators and grading contractors both price uncertainty into their numbers, and clearing removes uncertainty.
Where it goes wrong is clearing everything on day one. Once a tree is down you cannot put it back, and the house-siting decision usually shifts after the survey and the septic evaluation come back.
How much of the lot should I clear for a house?
Clear the building envelope, the driveway approach, and enough working room around the footprint for equipment and material staging — then stop and look before deciding on anything else.
Builders need room to work: space for a concrete truck to turn, a lumber drop, and a dumpster. Too tight a clearing costs you in construction friction later.
But the trees closest to the house are usually the ones people most regret losing. Twenty years of shade on the west side of a house in Alabama is worth real money in cooling costs, and it is not something you can buy back.
Do I need to clear before or after the survey?
Get the survey first when boundaries or setbacks are in question. Clear first when the lot is too overgrown for the survey crew to work efficiently.
In practice a lot of wooded lots need a light pass along the boundary lines so the surveyor can shoot them, then the full clearing after the corners are set and the setbacks are known.
Either way, do not clear to a line you have not confirmed. On a build lot, setbacks and easements are as binding as the boundary itself.
Can you clear a driveway route on a wooded lot?
Yes. Opening the driveway approach is often the first thing that needs to happen, because nothing else — survey trucks, drill rigs, concrete, lumber — gets in without it.
We clear the route and the working width. Base rock, culverts, and drainage are the next contractor's work.
Where the route crosses a ditch, a wet crossing, or a steep pitch, that is worth discussing at the estimate; it often changes where the driveway should go, not just how it is cleared.
What about the stumps on a building site?
They have to come out where you are building, and they can usually stay everywhere else. Stumps under a foundation, a driveway, or a septic field are a problem; stumps in the woods behind the house are not.
Removing stumps only where they matter is meaningfully cheaper than grubbing an entire lot, and it disturbs far less soil.
Decide the footprint first, then remove stumps inside it. Doing it in the other order means paying to grub ground you end up not building on.
Do I need a permit to clear a lot in Cullman County?
Requirements vary by municipality and by what you are doing, so confirm with Cullman County or your city before work starts. Vegetation removal and soil-disturbing construction work are treated differently.
Two things that commonly apply: outdoor burning in Alabama generally requires an Alabama Forestry Commission permit — which mulching sidesteps entirely, since there is no pile — and construction that disturbs an acre or more of soil generally triggers ADEM stormwater requirements.
We will tell you what we have run into locally. For anything binding, get it from the county in writing, not from a contractor.